Kings Avenue

**Update on works – October 2021**

Additional 24 hour works will be taking place at our Kings Avenue site from Monday 11 October to Saturday 16 October as our tunnel crosses the Northern Line. During this time period we will need to deliver additional tunnel segments to site along with skips to remove the material dug out of the tunnel.

There will be an increase in traffic movements around the site during this period, though there should be no impact on parking or access to the site. We are working closely with Transport for London to minimise disruption from these works.

Additionally, there should be no increase in noise from daytime works during this time period, and all work overnight should fall within the limits set by Lambeth Council. However, we will be carrying out real-time monitoring to make sure we stay within these limits. We have also installed matting around any machinery that may produce additional noise, in order to limit this.

We apologise for any disruption this may cause. If you have any questions, please do not hesitate to contact us at the details below.

**

We are building a permanent shaft and headhouse at our site at Kings Avenue, in order to drive a tunnel boring machine to our reception site at Wimbledon. The site will also be receiving a tunnel boring machine from our existing substation site at New Cross. Excavated material will also be removed at this site.

Our site on Kings Avenue is located at the junction of Kings Avenue and Acre Lane.

We are building the tunnels and shafts under our permitted development rights, which means we do not need planning permission for the entire project.

There are points along the tunnel route where we will be building headhouses to cover the shafts. Headhouses are required for ventilation and as a permanent point of access for the tunnel once it is built. We have secured planning permission for the headhouse from the London Borough of Lambeth.

The granting of our planning application follows a series of public information events we held at various locations across our route during 2018, where members of the public found out more about our works and the wider project and gave us some helpful feedback. This was followed by a public information event, which we held in January 2020, ahead of the construction phase starting in March 2020.

Working hours:

  • Above ground work will take place from 8am to 6pm Monday to Friday, and 8am to 1pm on Saturdays. During the night our works will largely take place below ground. There will be no work on Sundays or Bank Holidays.
  • Occasional out of hours work may be necessary and we will keep you informed about this.

 Key facts:

  • Dimensions: The shaft will be approximately 15m in diameter and 35m in depth. The headhouse will have a maximum footprint of 9.5m long by 6m wide, reaching a maximum height of 4.6m.
  • Traffic movements: We anticipate there would be approximately 38 HGV movements per day during peak construction activity, while we build the tunnel.
  • Access: Our construction vehicles will leave the site from Acre Lane or Kings Avenue, before joining the A23 and/or A205

Timeline:

  • Works started in April 2020 and are due to finish in June 2025.
  • The tunnel is scheduled to be built between May 2021 and April 2023.
  • The headhouse is scheduled to be built between April 2024 and March 2025.

This section of the website will be kept up to date and our community relations helpline (0800 783 2855) remains open 24/7 to answer any questions. You can also email us at [email protected]